Mufaddal Park, Mazgaon
by Alamdar Infrastructure Pvt Ltd · Mazgaon, Mumbai 400010 · Map
- Launched
- Jan 20236 yrs 10 mths promised
- Possession (MahaRERA)
- Nov 2029Not extended
- Concrete structure
- 27%Mid-construction
- Booked
- 68 of 14049% · 66 in Jul 2026
- Buildings
- 10.6 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 78
- 2 BHK
- 62
- Total units
- 140
- Buildings
- 1
- Land
- 0.6 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 27% | 0% | 68 | |
| 100% | 24% | 0% | 66 | |
| 100% | 8% | 0% | 61 | |
| 98% | 0% | 0% | 7 |
"–" means MahaRERA shows no figure for that update.
About this project
Mufaddal Park by Alamdar Infrastructure Pvt Ltd is a 140-unit SRA-sanctioned project in Mazgaon, Mumbai 400010, launched in January 2023 with possession due in November 2029. 68 units booked out of total 140 units. The concrete structure (RCC) is 27% complete.
Read full summary
Mufaddal Park is an SRA-sanctioned project by Alamdar Infrastructure Pvt Ltd in Mazgaon, Mumbai 400010, registered with MahaRERA as P51900049088. It was launched in January 2023. It has 140 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is November 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 27% complete, final finishes not started.
68 units booked out of total 140 units (49%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 24% to 27%.