Esta Ranjit House, Mandvi

by Esta Ranjit House · Mandvi, Mumbai 400003 · Map

Launched
Feb 20232 yrs 10 mths originally promised
Possession (MahaRERA)
Oct 2027Extended by 1 yr 10 mths
Concrete structure
95%Mid-construction
Booked (free sale)
5 of 1828% · 15 rehab units
Buildings
1
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale5 booked out of 18 units

Rehab15 units for existing members

Land-owner share10 units, not for sale

Total 43 units. Rehab and land-owner units are not for sale.

Project facts

Other units
43
Total units
43
Buildings
1
Phases
1
MahaRERA complaints
0
Free-sale units
18
Rehab units
15
Land-owner share (not for sale)
10

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)95%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 84%Dec 2025: Concrete structure (RCC) 84%Jul 2026: Concrete structure (RCC) 95%Oct 2026: Concrete structure (RCC) 95%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 95%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%95%0%5
100%95%0%5
100%84%0%3
100%84%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Esta Ranjit House by Esta Ranjit House is a 43-unit BMC-sanctioned project in Mandvi, Mumbai 400003, launched in February 2023 with possession due in October 2027. 5 units booked out of 18 units for sale. The concrete structure (RCC) is 95% complete.

Read full summary

Esta Ranjit House is a BMC-sanctioned project by Esta Ranjit House in Mandvi, Mumbai 400003, registered with MahaRERA as P51900049166. It was launched in February 2023. It has 43 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 43 units, 18 are for sale, 15 are rehab units for existing members and 10 are the land-owner's share, not for sale.

Its registered possession date is October 2027, extended by 1 year 10 months from the original December 2025. Construction: excavation complete, structure (RCC) 95% complete, final finishes not started.

5 units booked out of 18 units for sale (28%).