Monopoli, Dadar East
by Mathuresh Infrapro Private Ltd · Dadar East, Mumbai 400014 · Map
- Launched
- Mar 20234 yrs 6 mths originally promised
- Possession (MahaRERA)
- Dec 2029Extended by 2 yrs 3 mths
- Concrete structure
- 66%Mid-construction
- Booked (free sale)
- 100 of 25240% · 4 rehab units
- Buildings
- 51.4 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale100 booked out of 252 units
Rehab4 units for existing members
Total 256 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 66
- 2 BHK
- 187
- 3 BHK
- 3
- Total units
- 256
- Buildings
- 5
- Land
- 1.4 acres
- Phases
- 1
- MahaRERA complaints
- 2
- Free-sale units
- 252
- Rehab units
- 4
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 66% | 60% | 100 | |
| 100% | 60% | 50% | 73 | |
| 100% | 59% | 2% | 53 | |
| 70% | 0% | 0% | 232 |
"–" means MahaRERA shows no figure for that update.
About this project
Monopoli by Mathuresh Infrapro Private Ltd is a 256-unit BMC-sanctioned project in Dadar East, Mumbai 400014, launched in March 2023 with possession due in December 2029. 100 units booked out of 252 units for sale. The concrete structure (RCC) is 66% complete.
Read full summary
Monopoli is a BMC-sanctioned project by Mathuresh Infrapro Private Ltd in Dadar East, Mumbai 400014, registered with MahaRERA as P51900049902. It was launched in March 2023. It has 256 units in 5 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 256 units, 252 are for sale and 4 are rehab units for existing members.
Its registered possession date is December 2029, extended by 2 years 3 months from the original September 2027. Construction: excavation complete, structure (RCC) 66% complete, final finishes 60% complete.
100 units booked out of 252 units for sale (40%). Since the July 2026 update, 27 more units have been booked and the reported concrete structure (RCC) has gone from 60% to 66%.