Skip to main content

Aakasa, Worli

by Techno Freshworld LLP · Worli, Mumbai 400030 · Map

Launched
Apr 20234 yrs 8 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
92%Mid-construction
Booked
33 of 33100%
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
16
4 BHK
15
5+ BHK
2
Total units
33
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)92%
Finishes, lifts and services70%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 60%Dec 2025: Concrete structure (RCC) 85%Jul 2026: Concrete structure (RCC) 90%Oct 2026: Concrete structure (RCC) 92%Dec 2024: Final finishes 20%Dec 2025: Final finishes 65%Jul 2026: Final finishes 65%Oct 2026: Final finishes 70%Excavation 100%Concrete structure (RCC) 92%Final finishes 70%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%92%70%33
100%90%65%33
100%85%65%28
100%60%20%13

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Aakasa by Techno Freshworld LLP is a 33-unit MHADA-sanctioned project in Worli, Mumbai 400030, launched in April 2023 with possession due in December 2027. 33 units booked out of total 33 units. The concrete structure (RCC) is 92% complete.

Read full summary

Aakasa is a MHADA-sanctioned project by Techno Freshworld LLP in Worli, Mumbai 400030, registered with MahaRERA as P51900050463. It was launched in April 2023. It has 33 units in 1 building, with 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 92% complete, final finishes 70% complete.

33 units booked out of total 33 units (100%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 90% to 92%.