The Imperial I, Tardeo
by Sdc Township Private Limited · Tardeo, Mumbai 400034 · Map
- Launched
- Apr 20236 yrs 8 mths promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 4%Mid-construction
- Booked
- 50 of 11842% · 38 in Jul 2026
- Buildings
- 12.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 3 BHK
- 15
- 4 BHK
- 81
- 5+ BHK
- 13
- Other units
- 9
- Total units
- 118
- Buildings
- 1
- Land
- 2.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Reserved units
- 9
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 4% | 0% | 50 | |
| 83% | 0% | 0% | 38 | |
| 83% | 0% | 0% | – | |
| 83% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
The Imperial I by Sdc Township Private Limited is a 118-unit SRA-sanctioned project in Tardeo, Mumbai 400034, launched in April 2023 with possession due in December 2029. 50 units booked out of total 118 units. The concrete structure (RCC) is 4% complete.
Read full summary
The Imperial I is an SRA-sanctioned project by Sdc Township Private Limited in Tardeo, Mumbai 400034, registered with MahaRERA as P51900050473. It was launched in April 2023. It has 118 units in 1 building: 109 homes (3, 4 and 5+ BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 4% complete, final finishes not started.
50 units booked out of total 118 units (42%). Since the July 2026 update, 12 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 4%.