Ratan Infinia, Dadar East
by Shree Shankheshwar Enterprises · Dadar East, Mumbai 400014 · Map
- Launched
- Apr 20233 yrs 8 mths originally promised
- Possession (MahaRERA)
- Dec 2029Extended by 3 yrs
- Concrete structure
- 5%Mid-construction
- Booked (free sale)
- 10 of 3926% · 81 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale10 booked out of 39 units
Rehab81 units for existing members
Total 120 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 79
- 2 BHK
- 17
- Other units
- 24
- Total units
- 120
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 39
- Rehab units
- 81
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 5% | 0% | 10 | |
| 100% | 0% | 0% | 10 | |
| 100% | 0% | 0% | 10 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Ratan Infinia by Shree Shankheshwar Enterprises is a 120-unit BMC-sanctioned project in Dadar East, Mumbai 400014, launched in April 2023 with possession due in December 2029. 10 units booked out of 39 units for sale. The concrete structure (RCC) is 5% complete.
Read full summary
Ratan Infinia is a BMC-sanctioned project by Shree Shankheshwar Enterprises in Dadar East, Mumbai 400014, registered with MahaRERA as P51900050506. It was launched in April 2023. It has 120 units in 1 building: 96 homes (1 and 2 BHK) and 24 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 120 units, 39 are for sale and 81 are rehab units for existing members.
Its registered possession date is December 2029, extended by 3 years from the original December 2026. Construction: excavation complete, structure (RCC) 5% complete, final finishes not started.
10 units booked out of 39 units for sale (26%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 5%.