Beaumonte Tower C Sale Bndg No 10 -Wing C, Sion
by Pilot Constructions Private Limited · Sion, Mumbai 400022 · Map
- Launched
- Apr 20234 yrs 8 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 0%Early stage
- Booked
- 63 of 24726% · 42 in Jul 2026
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 95
- 3 BHK
- 136
- Other units
- 16
- Total units
- 247
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 80% | 0% | 0% | 63 | |
| 80% | 0% | 0% | 42 | |
| 80% | 0% | 0% | 32 |
"–" means MahaRERA shows no figure for that update.
About this project
Beaumonte Tower C Sale Bndg No 10 -Wing C by Pilot Constructions Private Limited is a 247-unit SRA-sanctioned project in Sion, Mumbai 400022, launched in April 2023 with possession due in December 2027. 63 units booked out of total 247 units. Work on the concrete structure (RCC) has not started.
Read full summary
Beaumonte Tower C Sale Bndg No 10 -Wing C is an SRA-sanctioned project by Pilot Constructions Private Limited in Sion, Mumbai 400022, registered with MahaRERA as P51900050715. It was launched in April 2023. It has 247 units in 1 building: 231 homes (2 and 3 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation 80% complete, structure (RCC) not started, final finishes not started.
63 units booked out of total 247 units (26%). Since the July 2026 update, 21 more units have been booked.