Skip to main content

Kapil Tirth, Mahim

Ready to move

by Prathamesh Projects LLP · Mahim, Mumbai 400016 · Map

Launched
May 20233 yrs 1 mth originally promised
Possession (MahaRERA)
Dec 2026Extended by 6 mths
Concrete structure
100%Ready to move
Booked (free sale)
21 of 2584% · 7 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale21 booked out of 25 units

Rehab7 units for existing members

Total 32 units. Rehab units are not for sale.

Project facts

1 RK
1
1 BHK
7
2 BHK
2
3 BHK
11
4 BHK
3
Other units
8
Total units
32
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
25
Rehab units
7
Reserved units
10

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 27%Dec 2025: Concrete structure (RCC) 87%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%21
100%100%0%20
100%87%0%5
100%27%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Kapil Tirth by Prathamesh Projects LLP is a 32-unit BMC-sanctioned project in Mahim, Mumbai 400016, launched in May 2023 with possession due in December 2026. 21 units booked out of 25 units for sale. The concrete structure (RCC) is complete.

Read full summary

Kapil Tirth is a BMC-sanctioned project by Prathamesh Projects LLP in Mahim, Mumbai 400016, registered with MahaRERA as P51900050770. It was launched in May 2023. It has 32 units in 1 building: 24 homes (1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 32 units, 25 are for sale and 7 are rehab units for existing members.

Its registered possession date is December 2026, extended by 6 months from the original June 2026. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

21 units booked out of 25 units for sale (84%). Since the July 2026 update, 1 more unit has been booked.