Skip to main content

Pristine Heights, Parel

Ready to move

by Gold Sukh Lifescapes LLP · Parel, Mumbai 400012 · Map

Launched
May 20232 yrs 10 mths originally promised
Possession (MahaRERA)
Mar 2027Extended by 1 yr
Concrete structure
100%Ready to move
Booked
20 of 3067% · 17 in Jul 2026
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
25
2 BHK
5
Total units
30
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 5%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 87%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 50%Jul 2026: Final finishes 60%Oct 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%20
100%100%60%17
100%87%50%9
5%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Pristine Heights by Gold Sukh Lifescapes LLP is a 30-unit BMC-sanctioned project in Parel, Mumbai 400012, launched in May 2023 with possession due in March 2027. 20 units booked out of total 30 units. The concrete structure (RCC) is complete.

Read full summary

Pristine Heights is a BMC-sanctioned project by Gold Sukh Lifescapes LLP in Parel, Mumbai 400012, registered with MahaRERA as P51900050986. It was launched in May 2023. It has 30 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2027, extended by 1 year from the original March 2026. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

20 units booked out of total 30 units (67%). Since the July 2026 update, 3 more units have been booked.