Tajun Heights, Wadala East

by A-1 Enterprises · Wadala East, Mumbai 400037 · Map

Launched
May 20235 yrs 7 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
100%Nearing possession
Booked
54 of 7077% · 55 in Jul 2026
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
2
1 BHK
61
Other units
7
Total units
70
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Reserved units
37

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 45%Dec 2025: Concrete structure (RCC) 45%Jul 2026: Concrete structure (RCC) 90%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 20%Oct 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 100%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%50%54
100%90%20%55
100%45%0%55
100%45%0%10

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Tajun Heights by A-1 Enterprises is a 70-unit SRA-sanctioned project in Wadala East, Mumbai 400037, launched in May 2023 with possession due in December 2028. 54 units booked out of total 70 units. The concrete structure (RCC) is complete.

Read full summary

Tajun Heights is an SRA-sanctioned project by A-1 Enterprises in Wadala East, Mumbai 400037, registered with MahaRERA as P51900051125. It was launched in May 2023. It has 70 units in 1 building: 63 homes (1 RK and 1 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.

54 units booked out of total 70 units (77%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 90% to 100%.