Worli House, Worli
by Harbour Front Properties Private Limited · Worli, Mumbai 400018 · Map
- Launched
- Jun 20235 yrs 6 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 98%Mid-construction
- Booked (free sale)
- 0 of 180% · 17 rehab units
- Buildings
- 10.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 18 units
Rehab17 units for existing members
Total 35 units. Rehab units are not for sale.
Project facts
- 3 BHK
- 9
- 4 BHK
- 8
- 5+ BHK
- 1
- Other units
- 17
- Total units
- 35
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 18
- Rehab units
- 17
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 98% | 15% | 0 | |
| 100% | 89% | 10% | 0 | |
| 100% | 32% | 10% | 0 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Worli House by Harbour Front Properties Private Limited is a 35-unit BMC-sanctioned project in Worli, Mumbai 400018, launched in June 2023 with possession due in December 2028. 0 units booked out of 18 units for sale. The concrete structure (RCC) is 98% complete.
Read full summary
Worli House is a BMC-sanctioned project by Harbour Front Properties Private Limited in Worli, Mumbai 400018, registered with MahaRERA as P51900051378. It was launched in June 2023. It has 35 units in 1 building: 18 homes (3, 4 and 5+ BHK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 35 units, 18 are for sale and 17 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 98% complete, final finishes 15% complete.
0 units booked out of 18 units for sale (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 89% to 98%.