Skip to main content

Palazzo, Cumballa Hill

by Livstone Estates LLP · Cumballa Hill, Mumbai 400026 · Map

Launched
Jun 20233 yrs 6 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
85%Mid-construction
Booked (free sale)
2 of 1217% · 3 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale2 booked out of 12 units

Rehab3 units for existing members

Total 15 units. Rehab units are not for sale.

Project facts

2 BHK
2
3 BHK
13
Total units
15
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
12
Rehab units
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)85%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 15%Dec 2025: Concrete structure (RCC) 63%Jul 2026: Concrete structure (RCC) 85%Oct 2026: Concrete structure (RCC) 85%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 85%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%85%0%2
100%85%0%2
100%63%0%2
100%15%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Palazzo by Livstone Estates LLP is a 15-unit BMC-sanctioned project in Cumballa Hill, Mumbai 400026, launched in June 2023 with possession due in December 2026. 2 units booked out of 12 units for sale. The concrete structure (RCC) is 85% complete.

Read full summary

Palazzo is a BMC-sanctioned project by Livstone Estates LLP in Cumballa Hill, Mumbai 400026, registered with MahaRERA as P51900051762. It was launched in June 2023. It has 15 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 15 units, 12 are for sale and 3 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 85% complete, final finishes not started.

2 units booked out of 12 units for sale (17%).