Skip to main content

Sea Krest, Worli

by Sugee Developers Pvt Ltd · Worli, Mumbai 400030 · Map

Launched
Jul 20234 yrs 5 mths originally promised
Possession (MahaRERA)
Dec 2029Extended by 2 yrs
Concrete structure
0%Early stage
Booked
6 of 1540%
Buildings
10.8 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

4 BHK
15
Total units
15
Buildings
1
Land
0.8 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation75%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 75%Jul 2026: Excavation 75%Oct 2026: Excavation 75%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 75%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
75%0%0%6
75%0%0%–
75%0%0%–
0%0%0%6

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Sea Krest by Sugee Developers Pvt Ltd is a 15-unit project in Worli, Mumbai 400030, launched in July 2023 with possession due in December 2029. 6 units booked out of total 15 units. Work on the concrete structure (RCC) has not started.

Read full summary

Sea Krest is a project by Sugee Developers Pvt Ltd in Worli, Mumbai 400030, registered with MahaRERA as P51900051903. It was launched in July 2023. It has 15 units in 1 building, with 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, extended by 2 years from the original December 2027. Construction: excavation 75% complete, structure (RCC) not started, final finishes not started.

6 units booked out of total 15 units (40%).