- Launched
- Jul 20235 yrs 5 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 7 of 3818% · 44 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale7 booked out of 38 units
Rehab44 units for existing members
Total 82 units. Rehab units are not for sale.
Project facts
- 1 RK
- 2
- 1 BHK
- 63
- 2 BHK
- 3
- Other units
- 14
- Total units
- 82
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 38
- Rehab units
- 44
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 7 | |
| 100% | 100% | 100% | 7 | |
| 100% | 100% | 0% | – | |
| 100% | 58% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Vighnaharta Tejdil by Tejas Prakash Dharia is an 82-unit BMC-sanctioned project in Girgaon, Mumbai 400004, launched in July 2023 with possession due in December 2028. 7 units booked out of 38 units for sale. The concrete structure (RCC) is complete.
Read full summary
Vighnaharta Tejdil is a BMC-sanctioned project by Tejas Prakash Dharia in Girgaon, Mumbai 400004, registered with MahaRERA as P51900051958. It was launched in July 2023. It has 82 units in 1 building: 68 homes (1 RK, 1 BHK and 2 BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 82 units, 38 are for sale and 44 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
7 units booked out of 38 units for sale (18%).