- Launched
- Aug 20233 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 31 of 31100% · 48 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale31 booked out of 31 units
Rehab48 units for existing members
Total 79 units. Rehab units are not for sale.
Project facts
- Other units
- 79
- Total units
- 79
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 31
- Rehab units
- 48
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 31 | |
| 100% | 68% | 0% | 30 | |
| 100% | 68% | 0% | 30 | |
| 100% | 68% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Shankesh Crown by H. Mehta Realtors LLP is a 79-unit BMC-sanctioned project in Sion, Mumbai 400022, launched in August 2023 with possession due in December 2026. 31 units booked out of 31 units for sale. The concrete structure (RCC) is complete.
Read full summary
Shankesh Crown is a BMC-sanctioned project by H. Mehta Realtors LLP in Sion, Mumbai 400022, registered with MahaRERA as P51900052336. It was launched in August 2023. It has 79 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 79 units, 31 are for sale and 48 are rehab units for existing members.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
31 units booked out of 31 units for sale (100%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 68% to 100%.