Harbour Breeze, Mazgaon
by Mahendra Ravji Chheda · Mazgaon, Mumbai 400010 · Map
- Launched
- Aug 20234 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 57%Mid-construction
- Booked (free sale)
- 35 of 4480% · 49 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale35 booked out of 44 units
Rehab49 units for existing members
Total 93 units. Rehab units are not for sale.
Project facts
- 1 RK
- 1
- 1 BHK
- 35
- 2 BHK
- 34
- Other units
- 23
- Total units
- 93
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 44
- Rehab units
- 49
- Reserved units
- 6
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 57% | 10% | 35 | |
| 100% | 45% | 0% | 30 | |
| 90% | 0% | 0% | 20 | |
| 50% | 0% | 0% | 4 |
"–" means MahaRERA shows no figure for that update.
About this project
Harbour Breeze by Mahendra Ravji Chheda is a 93-unit BMC-sanctioned project in Mazgaon, Mumbai 400010, launched in August 2023 with possession due in December 2027. 35 units booked out of 44 units for sale. The concrete structure (RCC) is 57% complete.
Read full summary
Harbour Breeze is a BMC-sanctioned project by Mahendra Ravji Chheda in Mazgaon, Mumbai 400010, registered with MahaRERA as P51900052384. It was launched in August 2023. It has 93 units in 1 building: 70 homes (1 RK, 1 BHK and 2 BHK) and 23 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 93 units, 44 are for sale and 49 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 57% complete, final finishes 10% complete.
35 units booked out of 44 units for sale (80%). Since the July 2026 update, 5 more units have been booked and the reported concrete structure (RCC) has gone from 45% to 57%.