Meadows, Girgaon
by Celestial Globe (A.O.P.) · Girgaon, Mumbai 400004 · Map
- Launched
- Sep 20233 yrs 6 mths originally promised
- Possession (MahaRERA)
- Mar 2028Extended by 1 yr
- Concrete structure
- 80%Mid-construction
- Booked (free sale)
- 108 of 22847% · 275 rehab units
- Buildings
- 21 acre
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale108 booked out of 228 units
Rehab275 units for existing members
Total 503 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 144
- 2 BHK
- 143
- 3 BHK
- 83
- 4 BHK
- 17
- 5+ BHK
- 1
- Other units
- 115
- Total units
- 503
- Buildings
- 2
- Land
- 1 acre
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 228
- Rehab units
- 275
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 80% | 60% | 108 | |
| 100% | 100% | 38% | 33 | |
| 100% | 73% | 14% | 14 | |
| 100% | 28% | 4% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Meadows by Celestial Globe (A.O.P.) is a 503-unit BMC-sanctioned project in Girgaon, Mumbai 400004, launched in September 2023 with possession due in March 2028. 108 units booked out of 228 units for sale. The concrete structure (RCC) is 80% complete.
Read full summary
Meadows is a BMC-sanctioned project by Celestial Globe (A.O.P.) in Girgaon, Mumbai 400004, registered with MahaRERA as P51900052589. It was launched in September 2023. It has 503 units in 2 buildings: 388 homes (1, 2, 3, 4 and 5+ BHK) and 115 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 503 units, 228 are for sale and 275 are rehab units for existing members.
Its registered possession date is March 2028, extended by 1 year from the original March 2027. Construction: excavation complete, structure (RCC) 80% complete, final finishes 60% complete.
108 units booked out of 228 units for sale (47%). Since the July 2026 update, 75 more units have been booked, the reported concrete structure (RCC) has gone from 100% to 80% and the possession date has moved from March 2027 to March 2028.