Skip to main content

Aryam, Kalbadevi

Ready to move

by Myra Infrastructure · Kalbadevi, Mumbai 400002 · Map

Launched
Oct 20234 yrs 2 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
100%Ready to move
Booked (free sale)
25 of 3866% · 37 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale25 booked out of 38 units

Rehab37 units for existing members

Total 75 units. Rehab units are not for sale.

Project facts

1 BHK
10
2 BHK
56
Other units
9
Total units
75
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
38
Rehab units
37

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 5%Jul 2026: Final finishes 90%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%25
100%100%90%16
100%100%5%9
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Aryam by Myra Infrastructure is a 75-unit BMC-sanctioned project in Kalbadevi, Mumbai 400002, launched in October 2023 with possession due in December 2027. 25 units booked out of 38 units for sale. The concrete structure (RCC) is complete.

Read full summary

Aryam is a BMC-sanctioned project by Myra Infrastructure in Kalbadevi, Mumbai 400002, registered with MahaRERA as P51900052888. It was launched in October 2023. It has 75 units in 1 building: 66 homes (1 and 2 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 75 units, 38 are for sale and 37 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

25 units booked out of 38 units for sale (66%). Since the July 2026 update, 9 more units have been booked.