Raheja Amaltis, Sion

by K Raheja Corp Real Estate Private Limited · Sion, Mumbai 400022 · Map

Launched
Dec 2023First of 2 phases
Possession (MahaRERA)
Sep 2028Not extended
Concrete structure
94%Weighted across 2 phases
Booked
97 of 12975% · 86 in Jul 2026
Buildings
20.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
1
3 BHK
79
4 BHK
49
Total units
129
Buildings
2
Land
0.7 acres
Phases
2
MahaRERA complaints
0

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Raheja Amaltis - Wing A
Mid-construction
P519000541296394%60%
Raheja Amaltis - Wing B
Mid-construction
P519000541526694%89%
Show updates by phase

Raheja Amaltis - Wing A (P51900054129)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%94%0%38
100%56%0%28
100%0%0%13
85%0%0%0

"–" means MahaRERA shows no figure for that update.

Raheja Amaltis - Wing B (P51900054152)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%94%0%59
100%22%0%58
100%0%0%49
85%0%0%20

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)94%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 85%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 39%Oct 2026: Concrete structure (RCC) 94%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 94%Final finishes 0%

How to read construction stages

About this project

Raheja Amaltis by K Raheja Corp Real Estate Private Limited is a 129-unit BMC-sanctioned project in Sion, Mumbai 400022, registered with MahaRERA in 2 phases, with possession due in September 2028. 97 units booked out of total 129 units. The concrete structure (RCC) is 94% complete.

Read full summary

Raheja Amaltis is a BMC-sanctioned project by K Raheja Corp Real Estate Private Limited in Sion, Mumbai 400022, registered with MahaRERA as 2 phases (P51900054129, P51900054152). The first phase was launched in December 2023. Together the phases have 129 units in 2 buildings, with 2, 3 and 4 BHK homes as registered with MahaRERA. Both phases are active on MahaRERA.

The registered possession date is September 2028; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 94% complete and final finishes 0% complete. Neither phase has its structure complete.

97 units booked out of total 129 units (75%). Since the July 2026 update, 11 more units have been booked.

K Raheja Corp's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA12
Total units across these projects1,377
Completed without extending the possession date3
Completed after an extension1
Lapsed0
Under construction8
Possession date extended on the builder's application1
Typical time from launch to 100% structure4 years 4 months
MahaRERA complaints (filed by or against the builder), all K Raheja Corp projects3 (3 of 12 projects)