The Gateway, Sewri
by LH Residential Housing Private Limited · Sewri, Mumbai 400015 · Map
- Launched
- Feb 20244 yrs 7 mths promised
- Possession (MahaRERA)
- Sep 2028Not extended
- Concrete structure
- 69%Mid-construction
- Booked
- 320 of 35989% · 313 in Jul 2026
- Buildings
- 22.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 3
- 3 BHK
- 174
- 4 BHK
- 130
- 5+ BHK
- 45
- Other units
- 7
- Total units
- 359
- Buildings
- 2
- Land
- 2.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 69% | 0% | 320 | |
| 100% | 36% | 0% | 313 | |
| 100% | 2% | 0% | 280 | |
| 0% | 0% | 0% | 169 |
"–" means MahaRERA shows no figure for that update.
About this project
The Gateway by LH Residential Housing Private Limited is a 359-unit BMC-sanctioned project in Sewri, Mumbai 400015, launched in February 2024 with possession due in September 2028. 320 units booked out of total 359 units. The concrete structure (RCC) is 69% complete.
Read full summary
The Gateway is a BMC-sanctioned project by LH Residential Housing Private Limited in Sewri, Mumbai 400015, registered with MahaRERA as P51900054969. It was launched in February 2024. It has 359 units in 2 buildings: 352 homes (1 RK, 3 BHK, 4 BHK and 5+ BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is September 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 69% complete, final finishes not started.
320 units booked out of total 359 units (89%). Since the July 2026 update, 7 more units have been booked and the reported concrete structure (RCC) has gone from 36% to 69%.