Splendour, Mazgaon

by Netra Developers · Mazgaon, Mumbai 400010 · Map

Launched
Feb 20243 yrs 1 mth promised
Possession (MahaRERA)
Mar 2027Not extended
Concrete structure
0%Early stage
Booked (free sale)
8 of 3424% · 33 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale8 booked out of 34 units

Rehab33 units for existing members

Total 67 units. Rehab units are not for sale.

Project facts

1 RK
6
1 BHK
30
2 BHK
31
Total units
67
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
34
Rehab units
33

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation70%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 70%Dec 2025: Excavation 70%Jul 2026: Excavation 70%Oct 2026: Excavation 70%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 70%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
70%0%0%8
70%0%0%–
70%0%0%–
70%0%0%1

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Splendour by Netra Developers is a 67-unit BMC-sanctioned project in Mazgaon, Mumbai 400010, launched in February 2024 with possession due in March 2027. 8 units booked out of 34 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Splendour is a BMC-sanctioned project by Netra Developers in Mazgaon, Mumbai 400010, registered with MahaRERA as P51900055031. It was launched in February 2024. It has 67 units in 1 building, with 1 RK, 1 BHK and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 67 units, 34 are for sale and 33 are rehab units for existing members.

Its registered possession date is March 2027, unchanged since launch. Construction: excavation 70% complete, structure (RCC) not started, final finishes not started.

8 units booked out of 34 units for sale (24%).