Kalpataru One - Wing A, Worli
by Kalpataru Properties Limited · Worli, Mumbai 400018 · Map
- Launched
- Mar 20248 yrs promised
- Possession (MahaRERA)
- Mar 2032Not extended
- Concrete structure
- 3%Mid-construction
- Booked
- 37 of 11133% · 35 in Jul 2026
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 5+ BHK
- 111
- Total units
- 111
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 3% | 0% | 37 | |
| 7% | 0% | 0% | 35 | |
| 7% | 0% | 0% | – | |
| 7% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Kalpataru One - Wing A by Kalpataru Properties Limited is a 111-unit BMC-sanctioned project in Worli, Mumbai 400018, launched in March 2024 with possession due in March 2032. 37 units booked out of total 111 units. The concrete structure (RCC) is 3% complete.
Read full summary
Kalpataru One - Wing A is a BMC-sanctioned project by Kalpataru Properties Limited in Worli, Mumbai 400018, registered with MahaRERA as P51900055246. It was launched in March 2024. It has 111 units in 1 building, with 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is March 2032, unchanged since launch. Construction: excavation complete, structure (RCC) 3% complete, final finishes not started.
37 units booked out of total 111 units (33%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 3%.
Kalpataru's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 42 |
|---|---|
| Total units across these projects | 6,678 |
| Completed without extending the possession date | 19 |
| Completed after an extension | 8 |
| Lapsed | 0 |
| Under construction | 15 |
| Possession date extended on the builder's application | 9 |
| Typical time from launch to 100% structure | 5 years 10 months |
| MahaRERA complaints (filed by or against the builder), all Kalpataru projects | 225 (21 of 42 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.