Maimoona Residency, Mumbai Central

by Kodia Enterprises · Mumbai Central, Mumbai 400008 · Map

Launched
Mar 20241 yr 9 mths originally promised
Possession (MahaRERA)
Dec 2028Extended by 3 yrs
Concrete structure
100%Nearing possession
Booked (free sale)
0 of 160% · 60 rehab units
Buildings
20.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 16 units

Rehab60 units for existing members

Total 76 units. Rehab units are not for sale.

Project facts

1 BHK
5
2 BHK
23
3 BHK
45
4 BHK
2
5+ BHK
1
Total units
76
Buildings
2
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
16
Rehab units
60

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services70%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Oct 2026Dec 2024: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Oct 2026: Final finishes 70%Excavation 100%Concrete structure (RCC) 100%Final finishes 70%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%70%0
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Maimoona Residency by Kodia Enterprises is a 76-unit BMC-sanctioned project in Mumbai Central, Mumbai 400008, launched in March 2024 with possession due in December 2028. 0 units booked out of 16 units for sale. The concrete structure (RCC) is complete.

Read full summary

Maimoona Residency is a BMC-sanctioned project by Kodia Enterprises in Mumbai Central, Mumbai 400008, registered with MahaRERA as P51900055260. It was launched in March 2024. It has 76 units in 2 buildings, with 1, 2, 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 76 units, 16 are for sale and 60 are rehab units for existing members.

Its registered possession date is December 2028, extended by 3 years from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes 70% complete.

0 units booked out of 16 units for sale (0%). Since the December 2024 update, the reported concrete structure (RCC) has gone from 0% to 100% and the possession date has moved from December 2025 to December 2028.