Zahra Residency, Mandvi
Ready to move
by Alliance Builders And Developers · Mandvi, Mumbai 400003 · Map
- Launched
- Apr 20242 yrs 8 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 17 of 2665% · 38 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale17 booked out of 26 units
Rehab38 units for existing members
Total 64 units. Rehab units are not for sale.
Project facts
- 1 RK
- 7
- 1 BHK
- 12
- 2 BHK
- 32
- 3 BHK
- 1
- Other units
- 12
- Total units
- 64
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 26
- Rehab units
- 38
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 99% | 17 | |
| 100% | 100% | 99% | 17 | |
| 100% | 100% | 97% | 13 | |
| 100% | 70% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Zahra Residency by Alliance Builders And Developers is a 64-unit BMC-sanctioned project in Mandvi, Mumbai 400003, launched in April 2024 with possession due in December 2026. 17 units booked out of 26 units for sale. The concrete structure (RCC) is complete.
Read full summary
Zahra Residency is a BMC-sanctioned project by Alliance Builders And Developers in Mandvi, Mumbai 400003, registered with MahaRERA as P51900055927. It was launched in April 2024. It has 64 units in 1 building: 52 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 64 units, 26 are for sale and 38 are rehab units for existing members.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 99% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
17 units booked out of 26 units for sale (65%).