Aqdas Residency, Chinchbunder
Ready to move
by M/s. Alamdar Kapde Developer · Chinchbunder, Mumbai 400009 · Map
- Launched
- May 20243 yrs 7 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 30 of 7242% · 60 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale30 booked out of 72 units
Rehab60 units for existing members
Total 132 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 113
- 2 BHK
- 6
- Other units
- 13
- Total units
- 132
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 72
- Rehab units
- 60
- Reserved units
- 4
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 30 | |
| 100% | 100% | 100% | 30 | |
| 100% | 95% | 80% | 30 | |
| 100% | 95% | 75% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Aqdas Residency by M/s. Alamdar Kapde Developer is a 132-unit BMC-sanctioned project in Chinchbunder, Mumbai 400009, launched in May 2024 with possession due in December 2027. 30 units booked out of 72 units for sale. The concrete structure (RCC) is complete.
Read full summary
Aqdas Residency is a BMC-sanctioned project by M/s. Alamdar Kapde Developer in Chinchbunder, Mumbai 400009, registered with MahaRERA as P51900056141. It was launched in May 2024. It has 132 units in 1 building: 119 homes (1 and 2 BHK) and 13 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 132 units, 72 are for sale and 60 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
30 units booked out of 72 units for sale (42%).