Skip to main content

Darshan Aura, Kalachowki

by Darshan Sky High Constructions LLP · Kalachowki, Mumbai 400033 · Map

Launched
May 20244 yrs 7 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
0%Early stage
Booked (free sale)
51 of 9255% · 102 rehab units
Buildings
20.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale51 booked out of 92 units

Rehab102 units for existing members

Total 194 units. Rehab units are not for sale.

Project facts

1 RK
2
1 BHK
134
2 BHK
41
Other units
17
Total units
194
Buildings
2
Land
0.7 acres
Phases
1
MahaRERA complaints
0
Free-sale units
92
Rehab units
102

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%51
100%0%0%51
100%0%0%51
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Darshan Aura by Darshan Sky High Constructions LLP is a 194-unit BMC-sanctioned project in Kalachowki, Mumbai 400033, launched in May 2024 with possession due in December 2028. 51 units booked out of 92 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Darshan Aura is a BMC-sanctioned project by Darshan Sky High Constructions LLP in Kalachowki, Mumbai 400033, registered with MahaRERA as P51900056427. It was launched in May 2024. It has 194 units in 2 buildings: 177 homes (1 RK, 1 BHK and 2 BHK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 194 units, 92 are for sale and 102 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

51 units booked out of 92 units for sale (55%).