Prestige Ocean Towers - South, Kalbadevi

by Prestige Projects Private Limited · Kalbadevi, Mumbai 400002 · Map

Launched
Jun 20246 yrs 6 mths promised
Possession (MahaRERA)
Dec 2030Not extended
Concrete structure
0%Early stage
Booked
191 of 19299% · 185 in Jul 2026
Buildings
11 acre
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

4 BHK
60
5+ BHK
5
Other units
127
Total units
192
Buildings
1
Land
1 acre
Phases
1
MahaRERA complaints
0
Reserved units
127

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%191
100%0%0%185
0%0%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Prestige Ocean Towers - South by Prestige Projects Private Limited is a 192-unit BMC-sanctioned project in Kalbadevi, Mumbai 400002, launched in June 2024 with possession due in December 2030. 191 units booked out of total 192 units. Work on the concrete structure (RCC) has not started.

Read full summary

Prestige Ocean Towers - South is a BMC-sanctioned project by Prestige Projects Private Limited in Kalbadevi, Mumbai 400002, registered with MahaRERA as P51900066470. It was launched in June 2024. It has 192 units in 1 building: 65 homes (4 and 5+ BHK) and 127 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2030, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

191 units booked out of total 192 units (99%). Since the July 2026 update, 6 more units have been booked.

Prestige's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA15
Total units across these projects5,057
Completed without extending the possession date3
Completed after an extension1
Lapsed0
Under construction11
Possession date extended on the builder's application2
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Prestige projects33 (5 of 15 projects)

See all Prestige projects →