Prestige Ocean Towers - South, Kalbadevi
by Prestige Projects Private Limited · Kalbadevi, Mumbai 400002 · Map
- Launched
- Jun 20246 yrs 6 mths promised
- Possession (MahaRERA)
- Dec 2030Not extended
- Concrete structure
- 0%Early stage
- Booked
- 191 of 19299% · 185 in Jul 2026
- Buildings
- 11 acre
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 4 BHK
- 60
- 5+ BHK
- 5
- Other units
- 127
- Total units
- 192
- Buildings
- 1
- Land
- 1 acre
- Phases
- 1
- MahaRERA complaints
- 0
- Reserved units
- 127
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 191 | |
| 100% | 0% | 0% | 185 | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Prestige Ocean Towers - South by Prestige Projects Private Limited is a 192-unit BMC-sanctioned project in Kalbadevi, Mumbai 400002, launched in June 2024 with possession due in December 2030. 191 units booked out of total 192 units. Work on the concrete structure (RCC) has not started.
Read full summary
Prestige Ocean Towers - South is a BMC-sanctioned project by Prestige Projects Private Limited in Kalbadevi, Mumbai 400002, registered with MahaRERA as P51900066470. It was launched in June 2024. It has 192 units in 1 building: 65 homes (4 and 5+ BHK) and 127 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2030, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.
191 units booked out of total 192 units (99%). Since the July 2026 update, 6 more units have been booked.
Prestige's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 15 |
|---|---|
| Total units across these projects | 5,057 |
| Completed without extending the possession date | 3 |
| Completed after an extension | 1 |
| Lapsed | 0 |
| Under construction | 11 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Prestige projects | 33 (5 of 15 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.