The Grand Tower No 1, Lower Parel

by Samir Narain Bhojwani · Lower Parel, Mumbai 400013 · Map

Launched
Jun 20243 yrs 7 mths promised
Possession (MahaRERA)
Jan 2028Not extended
Concrete structure
91%Mid-construction
Booked
0 of 1030%
Buildings
20.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

4 BHK
87
5+ BHK
16
Total units
103
Buildings
2
Land
0.6 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)91%
Finishes, lifts and services1%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 85%Dec 2025: Concrete structure (RCC) 91%Jul 2026: Concrete structure (RCC) 91%Oct 2026: Concrete structure (RCC) 91%Dec 2024: Final finishes 0%Dec 2025: Final finishes 1%Jul 2026: Final finishes 1%Oct 2026: Final finishes 1%Excavation 100%Concrete structure (RCC) 91%Final finishes 1%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%91%1%0
100%91%1%0
100%91%1%0
100%85%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

The Grand Tower No 1 by Samir Narain Bhojwani is a 103-unit BMC-sanctioned project in Lower Parel, Mumbai 400013, launched in June 2024 with possession due in January 2028. 0 units booked out of total 103 units. The concrete structure (RCC) is 91% complete.

Read full summary

The Grand Tower No 1 is a BMC-sanctioned project by Samir Narain Bhojwani in Lower Parel, Mumbai 400013, registered with MahaRERA as P51900076793. It was launched in June 2024. It has 103 units in 2 buildings, with 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is January 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 91% complete, final finishes 1% complete.

0 units booked out of total 103 units (0%).