Classic Heights, Mumbai Central

by Classic Enterprises · Mumbai Central, Mumbai 400008 · Map

Launched
Jul 20244 yrs 5 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
0%Early stage
Booked
–
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
16
1 BHK
17
2 BHK
13
Other units
25
Total units
71
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation50%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 50%Dec 2025: Excavation 50%Jul 2026: Excavation 50%Oct 2026: Excavation 50%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 50%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
50%0%0%–
50%0%0%–
50%0%0%–
50%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Classic Heights by Classic Enterprises is a 71-unit BMC-sanctioned project in Mumbai Central, Mumbai 400008, launched in July 2024 with possession due in December 2028. Work on the concrete structure (RCC) has not started.

Read full summary

Classic Heights is a BMC-sanctioned project by Classic Enterprises in Mumbai Central, Mumbai 400008, registered with MahaRERA as P51900077130. It was launched in July 2024. It has 71 units in 1 building: 46 homes (1 RK, 1 BHK and 2 BHK) and 25 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation 50% complete, structure (RCC) not started, final finishes not started.