The Manor, Grant Road

by Taksheel Reaalty LLP · Grant Road, Mumbai 400007 · Map

Launched
Aug 20243 yrs 4 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
85%Mid-construction
Booked (free sale)
5 of 956% · 17 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale5 booked out of 9 units

Rehab17 units for existing members

Total 26 units. Rehab units are not for sale.

Project facts

1 BHK
2
3 BHK
6
4 BHK
6
5+ BHK
1
Other units
11
Total units
26
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
9
Rehab units
17

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)85%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 75%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 85%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 85%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%85%50%5
100%0%0%–
100%0%0%–
75%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

The Manor by Taksheel Reaalty LLP is a 26-unit BMC-sanctioned project in Grant Road, Mumbai 400007, launched in August 2024 with possession due in December 2027. 5 units booked out of 9 units for sale. The concrete structure (RCC) is 85% complete.

Read full summary

The Manor is a BMC-sanctioned project by Taksheel Reaalty LLP in Grant Road, Mumbai 400007, registered with MahaRERA as P51900077289. It was launched in August 2024. It has 26 units in 1 building: 15 homes (1, 3, 4 and 5+ BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 26 units, 9 are for sale and 17 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 85% complete, final finishes 50% complete.

5 units booked out of 9 units for sale (56%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 85%.