Princecare Amaraa, Matunga
by Princecare Amaraa LLP · Matunga, Mumbai 400019 · Map
- Launched
- Aug 20243 yrs 9 mths originally promised
- Possession (MahaRERA)
- Mar 2029Extended by 10 mths
- Concrete structure
- 36%Mid-construction
- Booked (free sale)
- 6 of 3816% · 56 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale6 booked out of 38 units
Rehab56 units for existing members
Total 94 units. Rehab units are not for sale.
Project facts
- 1 RK
- 5
- 1 BHK
- 37
- 2 BHK
- 29
- 3 BHK
- 22
- 4 BHK
- 1
- Total units
- 94
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 38
- Rehab units
- 56
- Reserved units
- 4
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 36% | 0% | 6 | |
| 100% | 19% | 0% | 5 | |
| 100% | 4% | 0% | 2 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Princecare Amaraa by Princecare Amaraa LLP is a 94-unit BMC-sanctioned project in Matunga, Mumbai 400019, launched in August 2024 with possession due in March 2029. 6 units booked out of 38 units for sale. The concrete structure (RCC) is 36% complete.
Read full summary
Princecare Amaraa is a BMC-sanctioned project by Princecare Amaraa LLP in Matunga, Mumbai 400019, registered with MahaRERA as P51900077461. It was launched in August 2024. It has 94 units in 1 building, with 1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 94 units, 38 are for sale and 56 are rehab units for existing members.
Its registered possession date is March 2029, extended by 10 months from the original May 2028. Construction: excavation complete, structure (RCC) 36% complete, final finishes not started.
6 units booked out of 38 units for sale (16%). Since the July 2026 update, 1 more unit has been booked, the reported concrete structure (RCC) has gone from 19% to 36% and the possession date has moved from May 2028 to March 2029.