Skip to main content

Puje Ananta, Matunga

by Dalpatraj Pukhraj Jain · Matunga, Mumbai 400019 · Map

Launched
Oct 20245 yrs 2 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
8 of 3126% · 28 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale8 booked out of 31 units

Rehab28 units for existing members

Total 59 units. Rehab units are not for sale.

Project facts

1 RK
5
1 BHK
14
2 BHK
9
3 BHK
11
4 BHK
7
Other units
13
Total units
59
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
31
Rehab units
28

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%8
100%0%0%2
0%0%0%2
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400019

Projects with 20–100 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400019
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 2 mths4 yrs 1 mth
Possession date extendedNo0 of 5
Possession date (MahaRERA)Dec 2029Dec 2028
Concrete structure (RCC)0%15%
Units booked (free sale)26%33%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Puje Ananta by Dalpatraj Pukhraj Jain is a 59-unit BMC-sanctioned project in Matunga, Mumbai 400019, launched in October 2024 with possession due in December 2029. 8 units booked out of 31 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Puje Ananta is a BMC-sanctioned project by Dalpatraj Pukhraj Jain in Matunga, Mumbai 400019, registered with MahaRERA as P51900077577. It was launched in October 2024. It has 59 units in 1 building: 46 homes (1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK) and 13 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 59 units, 31 are for sale and 28 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

8 units booked out of 31 units for sale (26%). Since the July 2026 update, 6 more units have been booked.