Avhad Oasis, Dadar West
by Hrub Builders LLP · Dadar West, Mumbai 400028 · Map
- Launched
- Oct 20243 yrs 2 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 90%Mid-construction
- Booked (free sale)
- 13 of 3043% · 41 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale13 booked out of 30 units
Rehab41 units for existing members
Total 71 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 17
- 2 BHK
- 51
- Other units
- 3
- Total units
- 71
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 30
- Rehab units
- 41
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 90% | 0% | 13 | |
| 100% | 59% | 0% | 3 | |
| 100% | 0% | 0% | 0 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Avhad Oasis by Hrub Builders LLP is a 71-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in October 2024 with possession due in December 2027. 13 units booked out of 30 units for sale. The concrete structure (RCC) is 90% complete.
Read full summary
Avhad Oasis is a BMC-sanctioned project by Hrub Builders LLP in Dadar West, Mumbai 400028, registered with MahaRERA as P51900077721. It was launched in October 2024. It has 71 units in 1 building: 68 homes (1 and 2 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 71 units, 30 are for sale and 41 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 90% complete, final finishes not started.
13 units booked out of 30 units for sale (43%). Since the July 2026 update, 10 more units have been booked and the reported concrete structure (RCC) has gone from 59% to 90%.