Lotus, Mandvi
by Shreem Reality · Mandvi, Mumbai 400003 · Map
- Launched
- Nov 20243 yrs 3 mths originally promised
- Possession (MahaRERA)
- Feb 2030Extended by 2 yrs
- Concrete structure
- 45%Mid-construction
- Booked (free sale)
- 4 of 577% · 115 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale4 booked out of 57 units
Rehab115 units for existing members
Total 172 units. Rehab units are not for sale.
Project facts
- 1 RK
- 1
- 1 BHK
- 1
- 2 BHK
- 2
- Other units
- 168
- Total units
- 172
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 57
- Rehab units
- 115
- Reserved units
- 4
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 45% | 0% | 4 | |
| 100% | 0% | 0% | 4 | |
| 100% | 0% | 0% | – | |
| 90% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Lotus by Shreem Reality is a 172-unit BMC-sanctioned project in Mandvi, Mumbai 400003, launched in November 2024 with possession due in February 2030. 4 units booked out of 57 units for sale. The concrete structure (RCC) is 45% complete.
Read full summary
Lotus is a BMC-sanctioned project by Shreem Reality in Mandvi, Mumbai 400003, registered with MahaRERA as P51900077966. It was launched in November 2024. It has 172 units in 1 building: 4 homes (1 RK, 1 BHK and 2 BHK) and 168 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 172 units, 57 are for sale and 115 are rehab units for existing members.
Its registered possession date is February 2030, extended by 2 years from the original February 2028. Construction: excavation complete, structure (RCC) 45% complete, final finishes not started.
4 units booked out of 57 units for sale (7%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 45%.