by Shreenath Realty · Dadar West, Mumbai 400028 · Map

Launched
Dec 20242 yrs 3 mths promised
Possession (MahaRERA)
Mar 2027Not extended
Concrete structure
0%Early stage
Booked
–
Buildings
20.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
77
2 BHK
6
Other units
14
Total units
97
Buildings
2
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation80%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 80%Jul 2026: Excavation 80%Oct 2026: Excavation 80%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 80%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
80%0%0%–
80%0%0%–
80%0%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Satguru Skylight by Shreenath Realty is a 97-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in December 2024 with possession due in March 2027. Work on the concrete structure (RCC) has not started.

Read full summary

Satguru Skylight is a BMC-sanctioned project by Shreenath Realty in Dadar West, Mumbai 400028, registered with MahaRERA as P51900078277. It was launched in December 2024. It has 97 units in 2 buildings: 83 homes (1 and 2 BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2027, unchanged since launch. Construction: excavation 80% complete, structure (RCC) not started, final finishes not started.