Vardhman Altura, Girgaon

by Vardhman Group Realbuild LLP · Girgaon, Mumbai 400004 · Map

Launched
Dec 20244 yrs promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
0%Early stage
Booked (free sale)
0 of 10% · 41 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 1 unit

Rehab41 units for existing members

Total 42 units. Rehab units are not for sale.

Project facts

1 BHK
1
2 BHK
16
3 BHK
8
Other units
17
Total units
42
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
1
Rehab units
41

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 0%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%0
0%0%0%0
0%0%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Vardhman Altura by Vardhman Group Realbuild LLP is a 42-unit BMC-sanctioned project in Girgaon, Mumbai 400004, launched in December 2024 with possession due in December 2028. 0 units booked out of 1 unit for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Vardhman Altura is a BMC-sanctioned project by Vardhman Group Realbuild LLP in Girgaon, Mumbai 400004, registered with MahaRERA as P51900078485. It was launched in December 2024. It has 42 units in 1 building: 25 homes (1, 2 and 3 BHK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 42 units, 1 is for sale and 41 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

0 units booked out of 1 unit for sale (0%).