Aplite Sapphire, Grant Road
by Aplite Developers LLP · Grant Road, Mumbai 400007 · Map
- Launched
- Dec 20244 yrs promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 14 of 2458% · 51 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale14 booked out of 24 units
Rehab51 units for existing members
Land-owner share2 units, not for sale
Total 77 units. Rehab and land-owner units are not for sale.
Project facts
- 1 BHK
- 39
- 2 BHK
- 38
- Total units
- 77
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 24
- Rehab units
- 51
- Land-owner share (not for sale)
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 14 | |
| 100% | 0% | 0% | 3 | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Aplite Sapphire by Aplite Developers LLP is a 77-unit BMC-sanctioned project in Grant Road, Mumbai 400007, launched in December 2024 with possession due in December 2028. 14 units booked out of 24 units for sale. The concrete structure (RCC) is complete.
Read full summary
Aplite Sapphire is a BMC-sanctioned project by Aplite Developers LLP in Grant Road, Mumbai 400007, registered with MahaRERA as P51900078543. It was launched in December 2024. It has 77 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 77 units, 24 are for sale, 51 are rehab units for existing members and 2 are the land-owner's share, not for sale.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.
14 units booked out of 24 units for sale (58%). Since the July 2026 update, 11 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 100%.