Kgn Residency, Mumbai Central
by Kgn Developers · Mumbai Central, Mumbai 400008 · Map
- Launched
- Feb 20253 yrs 10 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 94%Mid-construction
- Booked (free sale)
- 9 of 3426% · 57 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale9 booked out of 34 units
Rehab57 units for existing members
Total 91 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 63
- 2 BHK
- 3
- Other units
- 25
- Total units
- 91
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 34
- Rehab units
- 57
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 94% | 10% | 9 | |
| 100% | 92% | 0% | 6 | |
| 100% | 90% | 0% | 3 |
"–" means MahaRERA shows no figure for that update.
About this project
Kgn Residency by Kgn Developers is a 91-unit BMC-sanctioned project in Mumbai Central, Mumbai 400008, launched in February 2025 with possession due in December 2028. 9 units booked out of 34 units for sale. The concrete structure (RCC) is 94% complete.
Read full summary
Kgn Residency is a BMC-sanctioned project by Kgn Developers in Mumbai Central, Mumbai 400008, registered with MahaRERA as P51900079194. It was launched in February 2025. It has 91 units in 1 building: 66 homes (1 and 2 BHK) and 25 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 91 units, 34 are for sale and 57 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 94% complete, final finishes 10% complete.
9 units booked out of 34 units for sale (26%). Since the July 2026 update, 3 more units have been booked and the reported concrete structure (RCC) has gone from 92% to 94%.