Echjay House, Cumballa Hill

by E House Realty Private Limited · Cumballa Hill, Mumbai 400026 · Map

Launched
Feb 20255 yrs 4 mths promised
Possession (MahaRERA)
Jun 2030Not extended
Concrete structure
0%Early stage
Booked (free sale)
2 of 450% · 9 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale2 booked out of 4 units

Rehab9 units for existing members

Total 13 units. Rehab units are not for sale.

Project facts

1 BHK
4
2 BHK
4
3 BHK
2
4 BHK
3
Total units
13
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
4
Rehab units
9

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 39%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%2
100%0%0%0
39%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Echjay House by E House Realty Private Limited is a 13-unit BMC-sanctioned project in Cumballa Hill, Mumbai 400026, launched in February 2025 with possession due in June 2030. 2 units booked out of 4 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Echjay House is a BMC-sanctioned project by E House Realty Private Limited in Cumballa Hill, Mumbai 400026, registered with MahaRERA as P51900079358. It was launched in February 2025. It has 13 units in 1 building, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 13 units, 4 are for sale and 9 are rehab units for existing members.

Its registered possession date is June 2030, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

2 units booked out of 4 units for sale (50%). Since the July 2026 update, 2 more units have been booked.