Viyaara Altiora, Mahim
by Structure Creators · Mahim, Mumbai 400016 · Map
- Launched
- Mar 20254 yrs 9 mths promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 42%Mid-construction
- Booked (free sale)
- 28 of 3874% · 54 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale28 booked out of 38 units
Rehab54 units for existing members
Total 92 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 55
- 2 BHK
- 26
- Other units
- 11
- Total units
- 92
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 38
- Rehab units
- 54
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 42% | 0% | 28 | |
| 100% | 0% | 0% | 25 | |
| 100% | 0% | 0% | 16 |
"–" means MahaRERA shows no figure for that update.
About this project
Viyaara Altiora by Structure Creators is a 92-unit BMC-sanctioned project in Mahim, Mumbai 400016, launched in March 2025 with possession due in December 2029. 28 units booked out of 38 units for sale. The concrete structure (RCC) is 42% complete.
Read full summary
Viyaara Altiora is a BMC-sanctioned project by Structure Creators in Mahim, Mumbai 400016, registered with MahaRERA as P51900079377. It was launched in March 2025. It has 92 units in 1 building: 81 homes (1 and 2 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 92 units, 38 are for sale and 54 are rehab units for existing members.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 42% complete, final finishes not started.
28 units booked out of 38 units for sale (74%). Since the July 2026 update, 3 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 42%.