Aqua Bay, Sewri

by Chamunda Infrastructure Limited · Sewri, Mumbai 400015 · Map

Launched
Mar 20253 yrs 9 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
18%Mid-construction
Booked
38 of 6955%
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
21
2 BHK
30
3 BHK
11
Other units
7
Total units
69
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Reserved units
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)18%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 70%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 10%Oct 2026: Concrete structure (RCC) 18%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 18%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%18%0%38
100%10%0%38
70%0%0%16

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Aqua Bay by Chamunda Infrastructure Limited is a 69-unit BMC-sanctioned project in Sewri, Mumbai 400015, launched in March 2025 with possession due in December 2028. 38 units booked out of total 69 units. The concrete structure (RCC) is 18% complete.

Read full summary

Aqua Bay is a BMC-sanctioned project by Chamunda Infrastructure Limited in Sewri, Mumbai 400015, registered with MahaRERA as P51900079685. It was launched in March 2025. It has 69 units in 1 building: 62 homes (1, 2 and 3 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 18% complete, final finishes not started.

38 units booked out of total 69 units (55%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 10% to 18%.