Shanti Square, Dadar East
by Shanti Siddhi Realtors LLP · Dadar East, Mumbai 400014 · Map
- Launched
- Apr 20254 yrs 8 mths promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 70%Mid-construction
- Booked (free sale)
- 2 of 1217% · 8 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale2 booked out of 12 units
Rehab8 units for existing members
Land-owner share2 units, not for sale
Total 22 units. Rehab and land-owner units are not for sale.
Project facts
- 3 BHK
- 1
- 4 BHK
- 2
- Other units
- 19
- Total units
- 22
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 12
- Rehab units
- 8
- Land-owner share (not for sale)
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 70% | 0% | 2 | |
| 100% | 15% | 0% | 0 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Shanti Square by Shanti Siddhi Realtors LLP is a 22-unit BMC-sanctioned project in Dadar East, Mumbai 400014, launched in April 2025 with possession due in December 2029. 2 units booked out of 12 units for sale. The concrete structure (RCC) is 70% complete.
Read full summary
Shanti Square is a BMC-sanctioned project by Shanti Siddhi Realtors LLP in Dadar East, Mumbai 400014, registered with MahaRERA as P51900079931. It was launched in April 2025. It has 22 units in 1 building: 3 homes (3 and 4 BHK) and 19 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 22 units, 12 are for sale, 8 are rehab units for existing members and 2 are the land-owner's share, not for sale.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 70% complete, final finishes not started.
2 units booked out of 12 units for sale (17%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 15% to 70%.