Markus Harmony, Mahim

by Markus Buildcon LLP · Mahim, Mumbai 400016 · Map

Launched
Apr 20252 yrs 3 mths originally promised
Possession (MahaRERA)
May 2028Extended by 10 mths
Concrete structure
0%Early stage
Booked (free sale)
–No units for sale
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free saleNo units for sale

Rehab9 units for existing members

Total 9 units. Rehab units are not for sale.

Project facts

1 BHK
9
Total units
9
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
0
Rehab units
9

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 15%Jul 2026: Excavation 90%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%0
90%0%0%0
15%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400016

Projects with up to 20 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400016
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 3 mths2 yrs 9 mths
Possession date extendedBy 10 mths0 of 3
Possession date (MahaRERA)May 2028Dec 2027
Concrete structure (RCC)0%0%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Markus Harmony by Markus Buildcon LLP is a 9-unit BMC-sanctioned project in Mahim, Mumbai 400016, launched in April 2025 with possession due in May 2028. No units for sale: rehab units only. Work on the concrete structure (RCC) has not started.

Read full summary

Markus Harmony is a BMC-sanctioned project by Markus Buildcon LLP in Mahim, Mumbai 400016, registered with MahaRERA as P51900079956. It was launched in April 2025. It has 9 units in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 9 units, none is for sale and 9 are rehab units for existing members.

Its registered possession date is May 2028, extended by 10 months from the original July 2027. Construction: excavation complete, structure (RCC) not started, final finishes not started.

No units for sale: rehab units only. Since the July 2026 update, the possession date has moved from July 2027 to May 2028.