Ajmal-235, Mumbai Central
by Awfi Real Estate Private Limited · Mumbai Central, Mumbai 400008 · Map
- Launched
- Apr 20254 yrs 3 mths promised
- Possession (MahaRERA)
- Jul 2029Not extended
- Concrete structure
- 9%Mid-construction
- Booked (free sale)
- 12 of 5422% · 156 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale12 booked out of 54 units
Rehab156 units for existing members
Total 210 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 111
- 2 BHK
- 49
- 3 BHK
- 8
- Other units
- 42
- Total units
- 210
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 54
- Rehab units
- 156
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 50% | 9% | 0% | 12 | |
| 0% | 0% | 0% | 0 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Ajmal-235 by Awfi Real Estate Private Limited is a 210-unit BMC-sanctioned project in Mumbai Central, Mumbai 400008, launched in April 2025 with possession due in July 2029. 12 units booked out of 54 units for sale. The concrete structure (RCC) is 9% complete.
Read full summary
Ajmal-235 is a BMC-sanctioned project by Awfi Real Estate Private Limited in Mumbai Central, Mumbai 400008, registered with MahaRERA as P51900080044. It was launched in April 2025. It has 210 units in 1 building: 168 homes (1, 2 and 3 BHK) and 42 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 210 units, 54 are for sale and 156 are rehab units for existing members.
Its registered possession date is July 2029, unchanged since launch. Construction: excavation 50% complete, structure (RCC) 9% complete, final finishes not started.
12 units booked out of 54 units for sale (22%). Since the July 2026 update, 12 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 9%.