KSA Imperia, Mumbai Central

by KSA Enterprises · Mumbai Central, Mumbai 400008 · Map

Launched
Jun 20255 yrs 6 mths promised
Possession (MahaRERA)
Dec 2030Not extended
Concrete structure
0%Early stage
Booked
–
Buildings
20.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
99
2 BHK
2
3 BHK
1
4 BHK
1
5+ BHK
1
Other units
40
Total units
144
Buildings
2
Land
0.5 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%–
0%0%0%–
0%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

KSA Imperia by KSA Enterprises is a 144-unit BMC-sanctioned project in Mumbai Central, Mumbai 400008, launched in June 2025 with possession due in December 2030. Work on the concrete structure (RCC) has not started.

Read full summary

KSA Imperia is a BMC-sanctioned project by KSA Enterprises in Mumbai Central, Mumbai 400008, registered with MahaRERA as P51900080418. It was launched in June 2025. It has 144 units in 2 buildings: 104 homes (1, 2, 3, 4 and 5+ BHK) and 40 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2030, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.