Skip to main content

Kshitij Omkar, Prabhadevi

by Omkar CHS Ltd · Prabhadevi, Mumbai 400025 · Map

Launched
Jun 20255 yrs 5 mths promised
Possession (MahaRERA)
Nov 2030Not extended
Concrete structure
0%Early stage
Booked (free sale)
23 of 3861% · 57 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale23 booked out of 38 units

Rehab57 units for existing members

Total 95 units. Rehab units are not for sale.

Project facts

1 BHK
55
2 BHK
35
3 BHK
3
4 BHK
1
Other units
1
Total units
95
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
38
Rehab units
57
Reserved units
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%23
100%0%0%0
0%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Kshitij Omkar by Omkar CHS Ltd is a 95-unit BMC-sanctioned project in Prabhadevi, Mumbai 400025, launched in June 2025 with possession due in November 2030. 23 units booked out of 38 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Kshitij Omkar is a BMC-sanctioned project by Omkar CHS Ltd in Prabhadevi, Mumbai 400025, registered with MahaRERA as P51900080430. It was launched in June 2025. It has 95 units in 1 building: 94 homes (1, 2, 3 and 4 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 95 units, 38 are for sale and 57 are rehab units for existing members.

Its registered possession date is November 2030, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

23 units booked out of 38 units for sale (61%). Since the July 2026 update, 23 more units have been booked.