W291, Malabar Hill
by Suparshva Incorporation · Malabar Hill, Mumbai 400006 · Map
- Launched
- Jun 20256 yrs 6 mths promised
- Possession (MahaRERA)
- Dec 2031Not extended
- Concrete structure
- 0%Early stage
- Booked
- –
- Buildings
- 10.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 3
- 1 BHK
- 9
- 2 BHK
- 27
- 3 BHK
- 15
- 4 BHK
- 16
- Total units
- 70
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Work not started as of Oct 2026
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | – |
"–" means MahaRERA shows no figure for that update.
About this project
W291 by Suparshva Incorporation is a 70-unit BMC-sanctioned project in Malabar Hill, Mumbai 400006, launched in June 2025 with possession due in December 2031. Work on the concrete structure (RCC) has not started.
Read full summary
W291 is a BMC-sanctioned project by Suparshva Incorporation in Malabar Hill, Mumbai 400006, registered with MahaRERA as P51900080495. It was launched in June 2025. It has 70 units in 1 building, with 1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2031, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.