Island Cove Tower 3, Mahim

by LH Residential Housing Private Limited, Shree Nidhi Concepts Realtor Pvt Ltd and Bhoomi Habitat · Mahim, Mumbai 400016 · Map

Launched
Jun 20254 yrs 6 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
0%Early stage
Booked
102 of 13476% · 93 in Jul 2026
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
64
3 BHK
66
Other units
4
Total units
134
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation90%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 15%Oct 2026: Excavation 90%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 90%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
90%0%0%102
15%0%0%93
0%0%0%63

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Island Cove Tower 3 by LH Residential Housing Private Limited, Shree Nidhi Concepts Realtor Pvt Ltd and Bhoomi Habitat is a 134-unit SRA-sanctioned project in Mahim, Mumbai 400016, launched in June 2025 with possession due in December 2029. 102 units booked out of total 134 units. Work on the concrete structure (RCC) has not started.

Read full summary

Island Cove Tower 3 is an SRA-sanctioned project by LH Residential Housing Private Limited, Shree Nidhi Concepts Realtor Pvt Ltd and Bhoomi Habitat in Mahim, Mumbai 400016, registered with MahaRERA as P51900080584. It was launched in June 2025. It has 134 units in 1 building: 130 homes (2 and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation 90% complete, structure (RCC) not started, final finishes not started.

102 units booked out of total 134 units (76%). Since the July 2026 update, 9 more units have been booked.