Skip to main content

Atlas Residency A and B, Mahalaxmi

by Atlas Infratech PvtLtd · Mahalaxmi, Mumbai 400011 · Map

Launched
Jun 20253 yrs 6 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
0%Early stage
Booked
–
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
9
1 BHK
9
2 BHK
6
3 BHK
3
Other units
25
Total units
52
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%–
100%0%0%–
100%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Atlas Residency A and B by Atlas Infratech PvtLtd is a 52-unit BMC-sanctioned project in Mahalaxmi, Mumbai 400011, launched in June 2025 with possession due in December 2028. Work on the concrete structure (RCC) has not started.

Read full summary

Atlas Residency A and B is a BMC-sanctioned project by Atlas Infratech PvtLtd in Mahalaxmi, Mumbai 400011, registered with MahaRERA as P51900080731. It was launched in June 2025. It has 52 units in 1 building: 27 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 25 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.