Salsette27 Centre, Byculla

by Goodtime Real Estate Development Private Limited · Byculla, Mumbai 400027 · Map

Launched
Sep 20252 yrs 6 mths promised
Possession (MahaRERA)
Mar 2028Not extended
Concrete structure
44%Mid-construction
Booked
25 of 25100%
Buildings
14.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
25
Total units
25
Buildings
1
Land
4.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)44%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 44%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 44%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%44%0%25
100%0%0%25
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Salsette27 Centre by Goodtime Real Estate Development Private Limited is a 25-unit BMC-sanctioned project in Byculla, Mumbai 400027, launched in September 2025 with possession due in March 2028. 25 units booked out of total 25 units. The concrete structure (RCC) is 44% complete.

Read full summary

Salsette27 Centre is a BMC-sanctioned project by Goodtime Real Estate Development Private Limited in Byculla, Mumbai 400027, registered with MahaRERA as PC1170002500854. It was launched in September 2025. It has 25 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 44% complete, final finishes not started.

25 units booked out of total 25 units (100%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 44%.